- In Interim Funding sources, separated ‘assemble req’d attachments’ task from ‘draft application’ task.
- Made significant changes to HUD 202/811 app section (primarily Firm Commitment and Closing processes). (It’s probably easiest just to replace those sections if you’re planning a 202/811 app.)
- Added a basic ‘Outside City of Seattle’ community notification process.
- Set Environmental Site Assessment Phase 2 as predecessor to all funding applications, but set its duration to 0 so will not over-estimate time required to prep those apps. Developer will need to set its duration to appropriate number if ESA Phase 1 determines Phase 2 to be necessary.
Tuesday, May 15, 2007
Project template updates, 5/15/07
I've made a few more changes to the MSP development project template, as follows. (Mostly minor except for a major reworking of the HUD 202/811 section.)